Developing a Change Calendar to Manage Change Schedules

Tuesday, February 9th, 2010

A change calendar is an important part of a well-designed change management process. An effective change calendar does not need to be a fancy integrated tool or part of an expensive change management system. In fact, your change calendar can be as simple as a published document showing all the approved changes for a given time period.

The change calendar drives the Change Advisory Board (CAB) meeting. Each change listed on the calendar is briefly reviewed, and the change owner (present at the meeting) attests to the readiness of that particular change for implementation. The items on the change calendar are separated into either “approved” and “pending” changes.

The approved changes are the items that have passed the standards of readiness already in place. For example, an approved change will have testing evidence as well as the required managerial approvals attached. Prior to the meeting, the CAB will have reviewed all submitted changes and classified each change as approved or pending. On the other hand, a change may be classified as pending because required approvals were not obtained before the CAB meeting. Furthermore, depending on the local practices, the CAB manager may approve such change requests for implementation the following week if the submitter succeeds in obtaining the required approvals by close of business on the following Monday.
Change Approval Process

Another important indicator on the change calendar is the planned implementation time—it indicates whether a specific change can be implemented during regular business hours or after business hours. For example, a change that may require shutting down a software system or turning off a piece of hardware may need to be implemented after business hours in order to not interfere with the normal operation of the business.

Moreover, the change calendar typically lists the names and contact information of the change requesters and the release and deployment managers, so that when necessary, parties can reach each other. Depending on the volume of change in a particular environment, an open phone bridge may be a standard arrangement to facilitate after-hours communication.

Risk Assessment to Change Implementation Time

Lastly, the summary section of the change calendar document lists any known future changes that the development and support community need to be aware of, such as major planned downtime or major system upgrades that may require action on their part.